Bil.
|
Butiran
Kerja
|
Perancangan
(%)
|
Sebenar (%)
|
1
|
Preliminaries
|
47%
|
47%
|
2
|
Pembersihan
tapak
|
100%
|
100%
|
3
|
Kerja
tanah
|
100%
|
60%
|
4
|
Kerja
Cerucuk
|
100%
|
99%
|
5
|
BANGUNAN PEJABAT
Pengorekan
|
100%
|
99%
|
6
|
Pile caps & stumps
|
100%
|
81%
|
7
|
Ground beams
|
100%
|
45%
|
8
|
Ground slab
|
100%
|
26%
|
9
|
Peringkat
Reka Bentuk IBS
|
100%
|
100%
|
10
|
Komponen IBS
|
15%
|
4%
|
11
|
BLOK MEKANIKAL
Pengorekan
Untuk Penapak
|
100%
|
100%
|
12
|
Penapak
|
100%
|
100%
|
13
|
Ground beams
|
100%
|
100%
|
|
TOTAL
|
13.05%
|
7.08%
|
Khamis, 27 September 2012
Perkembangan kerja-kerja di Bangunan Baru LPJ
PERKEMBANGAN KERJA DI BANGUNAN BARU LPJ